INTEC CPP-603 Basin Water Treatment System Closure: Process Design
Kimmitt, Raymond Rodney ; Faultersack, Wendell Gale ; Foster, Jonathan Kay ; Berry, Stephen Michael
Idaho National Laboratory
关键词: Removal;    Testing;    Mockup;    Pipelines;    Process Design;   
DOI  :  10.2172/910971
RP-ID  :  INEEL/EXT-02-01139
RP-ID  :  DE-AC07-99ID-13727
RP-ID  :  910971
美国|英语
来源: UNT Digital Library
PDF
【 摘 要 】

This document describes the engineering activities that have been completed in support of the closure plan for the Idaho Nuclear Technology and Engineering Center (INTEC) CPP-603 Basin Water Treatment System. This effort includes detailed assessments of methods and equipment for performing work in four areas: 1. A cold (nonradioactive) mockup system for testing equipment and procedures for vessel cleanout and vessel demolition. 2. Cleanout of process vessels to meet standards identified in the closure plan. 3. Dismantlement and removal of vessels, should it not be possible to clean them to required standards in the closure plan. 4. Cleanout or removal of pipelines and pumps associated with the CPP-603 basin water treatment system. Cleanout standards for the pipes will be the same as those used for the process vessels.

【 预 览 】
附件列表
Files Size Format View
910971.pdf 17405KB PDF download
  文献评价指标  
  下载次数:17次 浏览次数:42次