Study on construction schedule optimization of bored pile based on genetic algorithm
生态环境科学
Hu, Hesong^1 ; Ji, Xuan^1^2 ; Liang, Huqing^3
Guangzhou Institute of Building Science Co., Ltd, Guangzhou
510440, China^1
South China University of Technology, College of Software, Guangzhou
510006, China^2
Guangzhou Construction Group Co., Ltd, Guangzhou
510030, China^3
关键词: Construction management;    Construction progress;    Construction schedules;    Information levels;    Management method;    Operating process;    Site construction;    Working efficiency;   
Others  :  https://iopscience.iop.org/article/10.1088/1755-1315/300/2/022020/pdf
DOI  :  10.1088/1755-1315/300/2/022020
学科分类:环境科学(综合)
来源: IOP
PDF
【 摘 要 】
The site construction management of traditional filling pile has some disadvantages such as redundancy of data, difficulty in finding data, low working efficiency and poor timeliness. Thus, combined with the actual needs of filling pile construction management, based on the Java language, the mobile phone client of filling pile construction information management system was developed, and the mobile client system framework, operating process and functional framework were designed and illustrated. The software provided an advanced management method for the filling pile construction, it had great value to guarantee the construction progress and improve the information level of construction management.