Hydroacoustic Evaluation of Juvenile Salmonid Passage at The Dalles Dam Sluiceway, 2005
Johnson, Gary E. ; Khan, Fenton ; Hedgepeth, J ; Mueller, Robert P. ; Rakowski, Cynthia L. ; Richmond, Marshall C. ; Serkowski, John A. ; Skalski, John R.
Pacific Northwest National Laboratory (U.S.)
关键词: Salmonid Survival;    Columbia River;    Acoustic Camera;    Salmon;    Hydropower;   
DOI  :  10.2172/883215
RP-ID  :  PNNL-15540
RP-ID  :  AC05-76RL01830
RP-ID  :  883215
美国|英语
来源: UNT Digital Library
PDF
【 摘 要 】

The U.S. Army Corps of Engineers Portland District engaged the Pacific Northwest National Laboratory to evaluate fish passage at The Dalles Dam powerhouse in 2005. The goal of the study was to provide information on smolt passage that will inform decisions on long-term measures and operations to enhance sluiceway passage and reduce turbine passage to improve smolt survival at the dam. The study addressed one of the main programs dedicated to improving juvenile salmonid survival at The Dalles Dam: Surface Flow Bypass. The study objectives (see below) were met using a combination of hydroacoustic and hydraulic data. The study incorporated fixed-location hydroacoustic methods across the entire powerhouse, with especially intense sampling using multiple split-beam transducers at all sluiceway portals. We did not sample fish passage at the spillway in 2005. In the sluiceway nearfield, we used an acoustic camera to track fish movements. The fish data were interpreted with hydraulic data from a computational fluid dynamics (CFD) model. Fish passage data were collected in the framework of an “experiment” using a randomized block design (3-day treatments; two treatments) to compare two sluiceway operational configurations: Sluice 2+5 and Sluice 2+19 (six gates open for each configuration). Total project outflow was 76% of the 10-year average for spring and 71% of the 10-year average for summer. Based on these findings, we make the following recommendations: 1) The sluice should be operated 24 h/d from April until November. 2) Open six rather than three sluice gates to take advantage of the maximum hydraulic capacity of the sluiceway. 3) Open the three gates above the western-most operating main turbine unit and the three gates at MU 8 where turbine passage rates are relatively high. 4) Operate the turbine units below open sluice gates as a standard fish operations procedure. 5) Develop hydraulic and entrance enhancements to the sluiceway to tap the potential of The Dalles Dam sluiceway to be highly efficient and effective at passing juvenile salmonids. 6) Consider the following elements for surface flow bypasses during design of any sluiceway enhancements at The Dalles Dam: Form an extensive surface flow bypass flow net (surface bypass discharge greater than ~7% of total project discharge) at both west and east ends of the dam; Create a gradual increase in water velocity approaching the surface flow bypass (ideally, acceleration < 1 m/s per meter); Make water velocities at an entrance high enough (> 3 m/s) to entrain the subject juvenile fishes, e.g., 10,000 cfs or so; Adapt the shape and orientation of the surface entrance(s) to fit site-specific features, i.e., test a Removable Sluiceway Weir. 7)The Dalles Dam sluiceway has potential to be highly efficient and effective at passing juvenile salmonids. We recommend tapping this potential with enhancements to the sluiceway.

【 预 览 】
附件列表
Files Size Format View
883215.pdf 2229KB PDF download