National Ignition Facility Construction Safety Management Review
Warner, B.E.
Lawrence Livermore National Laboratory
关键词: Management;    Program Management;    Business;    70 Plasma Physics And Fusion Technology;    Us National Ignition Facility;   
DOI  :  10.2172/792434
RP-ID  :  UCRL-ID-137878
RP-ID  :  W-7405-Eng-48
RP-ID  :  792434
美国|英语
来源: UNT Digital Library
PDF
【 摘 要 】

An accident occurred at the NIF construction site on January 13, 2000, in which a worker sustained a serious injury when a 42-inch-diameter duct fell during installation. Following the accident, NIF Project Management chartered two review teams: (1) an Incident Analysis Team to independently assess the direct and root causes of the accident, and (2) a Management Review Team to review the roles and responsibilities of the line, support, and construction management organizations involved. This report provides a discussion of the information gathered by the Management Review Team and provides a list of observations and recommendations based on an analysis of the information. The Management Review Team includes senior managers who represent several Directorates within LLNL and DOE OAK: Dick Billia representing Engineering; Dave Leary representing Business Services and Public Affairs; Jim Jackson representing Hazards Control; Chuck Taylor representing DOE OAK; Arnie Clobes representing the ICF/NIF Program; and Jon Yatabe and Bruce Warner (Chairperson) representing the NIF Project. The attached letter from the NIF Project Manager, Ed Moses, to the Management Review Team contains the team's Charter. The team was asked to evaluate the effectiveness of the line management and its supporting safety functions in managing safety during NIF construction. The evaluation was to include the current conventional facility construction, which is 85% complete, and upcoming activities such as Beampath Infrastructure System installation, which will begin in the next six months and which represents a significant amount of work over the next two to three years. The remainder of this document describes the Management Review Team's review process (Section 2), its observations gathered during the review (Section 3), and its recommendations to the NIF Project Manager based on those observations (Section 4).

【 预 览 】
附件列表
Files Size Format View
792434.pdf 529KB PDF download
  文献评价指标  
  下载次数:15次 浏览次数:75次