PROGRESS REPORT: COFIRING PROJECTS FOR WILLOW ISLAND AND ALBRIGHT GENERATING STATIONS
Payette, K. ; Tillman, D.
National Energy Technology Laboratory (U.S.)
关键词: Materials Handling Equipment;    Fuels;    Performance Testing;    Storage Facilities;    20 Fossil-Fueled Power Plants;   
DOI  :  10.2172/785184
RP-ID  :  FC26-00NT40894--03
RP-ID  :  FC26-00NT40894
RP-ID  :  785184
美国|英语
来源: UNT Digital Library
PDF
【 摘 要 】

During the period April 1, 2001--June 30, 2001, Allegheny Energy Supply Co., LLC (Allegheny) accelerated construction of the Willow Island cofiring project, completed the installation of foundations for the fuel storage facility, the fuel receiving facility, and the processing building. Allegheny received all processing equipment to be installed at Willow Island. Allegheny completed the combustion modeling for the Willow Island project. During this time period construction of the Albright Generating Station cofiring facility was completed, with few items left for final action. The facility was dedicated at a ceremony on June 29. Initial testing of cofiring at the facility commenced. This report summarizes the activities associated with the Designer Opportunity Fuel program, and demonstrations at Willow Island and Albright Generating Stations. It details the construction activities at both sites along with the combustion modeling at the Willow Island site.

【 预 览 】
附件列表
Files Size Format View
785184.pdf 1217KB PDF download
  文献评价指标  
  下载次数:4次 浏览次数:22次