PowerGuard Advanced Manufacturing, PVMaT Phase II Technical Progress Report; 1 July 1999--30 September 2000 | |
Dinwoodie, T. L. ; Botkin, J. | |
National Renewable Energy Laboratory (U.S.) | |
关键词: Pv; 36 Materials Science; Progress Report; Pv System; Manufacturing; | |
DOI : 10.2172/783440 RP-ID : NREL/SR-520-30247 RP-ID : AC36-99GO10337 RP-ID : 783440 |
|
美国|英语 | |
来源: UNT Digital Library | |
【 摘 要 】
This project introduced incremental improvements to PowerGuard system components and manufacturing processes to significantly reduce the costs of a PowerGuard system. The improvement resulted in a lower cost, higher impact PV product. During Phase II, these accomplishments have resulted in: A production rate of greater than 400 PowerGuard tiles per shift (20 MW/year) manufacturing capacity; 57% cost reduction for PowerGuard tile; UL listing for four additional PowerGuard tiles configurations; Improved quality of finished goods due to improved tooling and processes in manufacturing, simultaneously improving throughput and lowering cost of $3.80Wp for large systems. In Phase III of this contract, PowerLight will continue efforts to improve the manufacturing processes for PowerGuard. Specific performance objectives during phase III are as follows: Demonstrate system cost reduction from $3.80/Wp to $3.05/Wp for large systems; Establish or assess the performance of dedicated PowerGuard PV module plant capacity of 2 MW per year; Complete wind tunnel testing of all design refinements; Produce an installation manual and training program for installing PowerGuard systems; Establish performance of manufacturing modifications based on assessment of commercial systems which incorporate the new features and processes; and Finalize UL, International Conference of Building Officials (ICBO), and international listings of PowerGuard improvements. These are expected to result in a lower cost, higher impact PV product, as sought by this program.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
783440.pdf | 630KB | download |