| Completion of Milestone 2.2.4.2.2/FY01/A ''Completion of Mechanical Assembly of PuCTF in the Plutonium Facility'' | |
| Brummond, W ; Armantrout, G | |
| Lawrence Livermore National Laboratory | |
| 关键词: Materials Handling Equipment; Installation; Gloveboxes; Radioactive Waste Processing; Robots; | |
| DOI : 10.2172/15005416 RP-ID : UCRL-ID-143640 RP-ID : W-7405-ENG-48 RP-ID : 15005416 |
|
| 美国|英语 | |
| 来源: UNT Digital Library | |
PDF
|
|
【 摘 要 】
The subject milestone was completed on March 1st. This milestone signifies the completion the mechanical installation and assembly of PuCTF in room 1345 in the LLNT Plutonium Facility. This installation included equipment both in room 1345 and in the loft, As reported in the last milestone, ''LLNL Pu Facility space prepared for installation of PUCTF'', milestone 6.2.2/Fy00/c, steel plates had been installed on the floor to support the PuCTF glovebox and equipment. The steel plate system was a substantial help in completing the mechanical installation reported here. The glovebox sections were brought into the room and attached together. Temporary seismic tie-down straps were used to brace the assembly. This temporary tie-down also provided Flexibility for alignment and adjustment. The internal equipment, (attritors, granulator, press feed shoe and die set, furnace, robot and powder transport system) were subsequently installed. The glovebox was then welded to the steel plates for permanent seismic anchoring. The control racks were attached to the floor and are ready for wiring and the press hydraulic power unit has been installed in the loft.
【 预 览 】