会议论文详细信息
Cryogenic Engineering Conference 2017
FRIB cryogenic system status
材料科学;物理学
Casagrande, F.^1 ; Ganni, V.^1 ; Knudsen, P.^1 ; Jones, S.^1 ; Sidi-Yekhlef, A.^1 ; Tatsumoto, H.^1 ; Nguyen, C.^1 ; Fila, A.^1 ; Vargas, G.^3 ; Dudley, C.^1 ; Joseph, N.^1 ; Stanley, S.^1 ; Dixon, K.^2 ; Norton, R.^2 ; Laverdure, N.^2 ; Yang, S.^2
Facility for Rare Isotope Beams (FRIB), Michigan State University (MSU), MI 48824 USA, East Lansing, United States^1
Thomas Jefferson National Accelerator Facility (TJNAF or 'Jlab'), Newport News
VA
23606, United States^2
Jacobs, Houston
TX
77058, United States^3
关键词: Commissioning plans;    Compressor systems;    Cryogenic system;    Distribution systems;    Helium refrigeration systems;    Process equipments;    Sub-systems;    Support systems;   
Others  :  https://iopscience.iop.org/article/10.1088/1757-899X/278/1/012102/pdf
DOI  :  10.1088/1757-899X/278/1/012102
学科分类:材料科学(综合)
来源: IOP
PDF
【 摘 要 】

Construction and installation of the FRIB 4.5 K helium refrigeration system is nearing completion, with compressor system commissioning and 4.5 K refrigerator commissioning on schedule to occur in late 2017. The LINAC 4.5 K helium distribution system, all major process equipment, and the cryogenic distribution for the sub-systems have been procured and delivered. The sub-atmospheric cold box fabrication is planned to begin the summer of 2017, which is on schedule for commissioning in the spring of 2018. Commissioning of the support systems, such as the helium gas storage, helium purifier, and oil processor is planned to be complete by the summer of 2017. This paper presents details of the equipment procured, installation status and commissioning plans.