2nd International Conference on Sustainable Development in Civil, Urban and Transportation Engineering | |
Semi top-down method combined with earth-bank, an effective method for basement construction. | |
地球科学;运输工程;经济学 | |
Tuan, B.Q.^1 ; Tam, Ng M^2 | |
Faculty of Civil Engineering, Ton Duc Thang University, Ho Chi Minh City, Viet Nam^1 | |
Faculty of Civil Engineering, Ho Chi Minh City University of Technology, Ho Chi Minh City, Viet Nam^2 | |
关键词: Bottom up; Bottom up methods; Construction method; Construction projects; Deep excavation; Open-cut method; Steel struts; Top-down methods; | |
Others : https://iopscience.iop.org/article/10.1088/1755-1315/143/1/012047/pdf DOI : 10.1088/1755-1315/143/1/012047 |
|
来源: IOP | |
【 摘 要 】
Choosing an appropriate method of deep excavation not only plays a decisive role in technical success, but also in economics of the construction project. Presently, we mainly base on to key methods: "Bottom-up" and "Top-down" construction method. Right now, this paper presents an another method of construction that is "Semi Top-down method combining with earth-bank" in order to take the advantages and limit the weakness of the above methods. The Bottom-up method was improved by using the earth-bank to stabilize retaining walls instead of the bracing steel struts. The Top-down method was improved by using the open cut method for the half of the earthwork quantities.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
Semi top-down method combined with earth-bank, an effective method for basement construction. | 2067KB | download |