Data Center Energy Benchmarking: Part 4. Case Study on a Computer-Testing Center (No. 21).
Xu, T. ; Greenberg, S.
Technical Information Center Oak Ridge Tennessee
关键词: Cooling load;    Electric power;    Energy efficiency;    Lighting systems;    Management;   
RP-ID  :  DE2008926298
学科分类:工程和技术(综合)
美国|英语
来源: National Technical Reports Library
PDF
【 摘 要 】

The data center in this study had a total floor area of 8,580 square feet (ft(sup 2)) with one-foot raised-floors. It was a rack lab with 440 racks, and was located in a 208,240 ft(sup 2) multi-story office building in San Jose, California. Since the data center was used only for testing equipment, it was not configured as a critical facility in terms of electrical and cooling supply. It did not have a dedicated chiller system but served by the main building chiller plant and make-up air system. Additionally, it was served by a single electrical supply with no provision for backup power. The data center operated on a 24 hour per day, year-round cycle, and users had all hour full access to the data center facility.

【 预 览 】
附件列表
Files Size Format View
DE2008926298.pdf 656KB PDF download