As-Built Verification Plan Spent Nuclear Fuel Canister Storage Building MCO Handling Machine.
Swenson, C. E.
Technical Information Center Oak Ridge Tennessee
关键词: Spent fuels;    Radioactive waste storage;    Verification;    Design criteria;    Safety engineering;   
RP-ID  :  DE2003805641
学科分类:工程和技术(综合)
美国|英语
来源: National Technical Reports Library
PDF
【 摘 要 】

This as-built verification plan outlines the methodology and responsibilities that will be implemented during the as-built field verification activity for the Canister Storage Building (CSB) MCO Handling Machine (MHM). This as-built verification plan covers the electrical portion of the construction performed by power city under contract to MOWAT. The as-built verifications will be performed in accordance Administrative Procedure AP 6-012-00, Spent Nuclear Fuel Project As-Built Verification Plan Development Process, revision I. The results of the verification walkdown will be documented in a verification walkdown completion package, approved by the Design Authority (DA), and maintained in the CSB project files.

【 预 览 】
附件列表
Files Size Format View
DE2003805641.pdf 593KB PDF download
  文献评价指标  
  下载次数:17次 浏览次数:11次