As-Built Verification Plan Spent Nuclear Fuel Canister Storage Building MCO Handling Machine | |
SWENSON, C.E. | |
Fluor Hanford, Inc. | |
关键词: Storage; Administrative Procedures; 11 Nuclear Fuel Cycle And Fuel Materials; Construction; Nuclear Fuels; | |
DOI : 10.2172/805641 RP-ID : SNF-6448, Rev.1 RP-ID : AC06-96RL13200 RP-ID : 805641 |
|
美国|英语 | |
来源: UNT Digital Library | |
【 摘 要 】
This as-built verification plan outlines the methodology and responsibilities that will be implemented during the as-built field verification activity for the Canister Storage Building (CSB) MCO HANDLING MACHINE (MHM). This as-built verification plan covers THE ELECTRICAL PORTION of the CONSTRUCTION PERFORMED BY POWER CITY UNDER CONTRACT TO MOWAT. The as-built verifications will be performed in accordance Administrative Procedure AP 6-012-00, Spent Nuclear Fuel Project As-Built Verification Plan Development Process, revision I. The results of the verification walkdown will be documented in a verification walkdown completion package, approved by the Design Authority (DA), and maintained in the CSB project files.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
805641.pdf | 598KB | download |