| 244-AR Vault Interim Stabilization Project Plan | |
| LANEY, T. | |
| CH2M Hill Hanford Group, Inc. | |
| 关键词: Sludges; Storage; Stabilization; Documentation; Personnel; | |
| DOI : 10.2172/801868 RP-ID : RPP-5635, Rev.0 RP-ID : AC27-99RL14047 RP-ID : 801868 |
|
| 美国|英语 | |
| 来源: UNT Digital Library | |
PDF
|
|
【 摘 要 】
The 244-AR Vault Facility, constructed between 1966 and 1968, was designed to provide lag storage and treatment for the Plutonium-Uranium Extraction Facility (PUREX) tank farm sludges. Tank farm personnel transferred the waste from the 244-AR Vault Facility to B Plant for recovery of cesium and strontium. B Plant personnel then transferred the treatment residuals back to the tank farms for storage of the sludge and liquids. The last process operations, which transferred waste supporting the cesium/strontium recovery mission, occurred in April 1978. After the final transfer in 1978, the 244-AR facility underwent a cleanout. However, 2,271 L (600 gal) of sludge were left in Tank 004AR from an earlier transfer from Tank 241-AX-104. When the cleanout was completed, the facility was placed in a standby status. The sludge had been transferred to Tank 004AR to support Pacific Northwest National Laboratory [PNNL] vitrification work. Documentation of waste transfers suggests that a portion of the sludge may have been moved from Tank 004AR to Tank 002AR in preparation for transfer back to the AX Tank Farm; however, quantities of the sludge that were moved to Tank 002AR from that transfer must be estimated.
【 预 览 】
| Files | Size | Format | View |
|---|---|---|---|
| 801868.pdf | 3641KB |
PDF