INTEGRATED SYSTEM TO CONTROL PRIMARY PM 2.5 FROM ELECTRIC POWER PLANTS | |
National Energy Technology Laboratory (U.S.) | |
关键词: Pollution Control Equipment; 01 Coal, Lignite, And Peat; Dry Scrubbers; Coal; Fossil-Fuel Power Plants; | |
DOI : 10.2172/789054 RP-ID : FC26-00NT40757--02 RP-ID : FC26-00NT40757 RP-ID : 789054 |
|
美国|英语 | |
来源: UNT Digital Library | |
【 摘 要 】
One of the major tasks of this project is to design and fabricate an Advanced ElectroCore field prototype system. The system is designed to handle 5,000 acfm of exhaust gas from a coal-fired power plant. The system consists of the Advanced ElectroCore module, a water-cooled precharger and a dry scrubber. The system is shown in Figure 1. LSR has completed the design drawings for the ElectroCore module and the water-cooled precharger. The design drawings for the dry scrubber are nearly complete. Merrick Environmental Technology, Inc. has completed most of the fabrication drawings for the ElectroCore module and for the water-cooled precharger. From the original schedule, the design task (Task 2) should have been completed by 15 July 2000. It now looks like this task will be finished by mid-October thereby putting the project about two months behind schedule. Much of the delay is due to design changes that will make this field prototype easier to transport and erect. These changes will make the unit much more valuable as an ElectroCore system sales tool at the end of this project.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
789054.pdf | 33KB | download |