Early Warning Look Ahead Metrics: The Percent Milestone Backlog Metric | |
Shinn, Stephen A. ; Anderson, Timothy P. | |
PID : NTRS Document ID: 20170002020 RP-ID : GSFC-E-DAA-TN39065 |
|
美国|英语 | |
来源: NASA Technical Reports Server | |
【 摘 要 】
All complex development projects experience delays and corresponding backlogs of their project control milestones during their acquisition lifecycles. NASA Goddard Space Flight Center (GSFC) Flight Projects Directorate (FPD) teamed with The Aerospace Corporation (Aerospace) to develop a collection of Early Warning Look Ahead metrics that would provide GSFC leadership with some independent indication of the programmatic health of GSFC flight projects. As part of the collection of Early Warning Look Ahead metrics, the Percent Milestone Backlog metric is particularly revealing, and has utility as a stand-alone execution performance monitoring tool. This paper describes the purpose, development methodology, and utility of the Percent Milestone Backlog metric. The other four Early Warning Look Ahead metrics are also briefly discussed. Finally, an example of the use of the Percent Milestone Backlog metric in providing actionable insight is described, along with examples of its potential use in other commodities.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
RO201705200000246LZ | 2624KB | download |