Early Warning Look Ahead Metrics: The Percent Milestone Backlog Metric
Shinn, Stephen A. ; Anderson, Timothy P.
PID  :  NTRS Document ID: 20170002020
RP-ID  :  GSFC-E-DAA-TN39065
美国|英语
来源: NASA Technical Reports Server
PDF
【 摘 要 】

All complex development projects experience delays and corresponding backlogs of their project control milestones during their acquisition lifecycles. NASA Goddard Space Flight Center (GSFC) Flight Projects Directorate (FPD) teamed with The Aerospace Corporation (Aerospace) to develop a collection of Early Warning Look Ahead metrics that would provide GSFC leadership with some independent indication of the programmatic health of GSFC flight projects. As part of the collection of Early Warning Look Ahead metrics, the Percent Milestone Backlog metric is particularly revealing, and has utility as a stand-alone execution performance monitoring tool. This paper describes the purpose, development methodology, and utility of the Percent Milestone Backlog metric. The other four Early Warning Look Ahead metrics are also briefly discussed. Finally, an example of the use of the Percent Milestone Backlog metric in providing actionable insight is described, along with examples of its potential use in other commodities.

【 预 览 】
附件列表
Files Size Format View
RO201705200000246LZ 2624KB PDF download
  文献评价指标  
  下载次数:12次 浏览次数:23次