Terahop and Lawrence Livermore National LaboratoryStructural Fire RF Testing | |
Haugen, P ; Pratt, G | |
关键词: A CENTERS; CONCRETES; DOORS; FIBERS; FLOORS; LAWRENCE LIVERMORE NATIONAL LABORATORY; MIXTURES; PLASMA; PLATES; SAFETY; SHIELDING; TESTING; THICKNESS; TRAINING; WINDOWS; FIRE FIGHTING; | |
DOI : 10.2172/902270 RP-ID : UCRL-TR-228526 PID : OSTI ID: 902270 Others : TRN: US200717%%514 |
|
学科分类:工程和技术(综合) | |
美国|英语 | |
来源: SciTech Connect | |
【 摘 要 】
The Georgia Public Safety Training Center's Live Fire Training Facility in Forsyth, GA is a three story structure constructed of rebar-reinforced concrete wall and floors. All the door and window coverings on the building are constructed of thick, plate metal to withstand the high temperatures generated inside the building during training exercises. All of the building's walls and floors are 1-foot thick, and regular concrete columns run up along the inside of the wall increasing the thickness to 20-inches in those locations. A center concrete staircase divides the structure in half. For typical exercises, fires are started in the back right corner of the building on the first floor and in the front right corner on the second floor as shown in Figure 2. Due to the high heat generated during these exercises, measured at 300 F on the floor and 700 F near the ceilings, there were limited locations at which equipment could be placed that did not incorporate heat shielding, such as the Lawrence Livermore National Laboratory's UWB system. However, upon inspection of the building, two preferable locations were identified in which equipment could be placed that would be protected from the temperature extremes generated by the fires. These locations are identified in Figure 2 as the tested TX locations. These were preferred locations because, while they protected the hardware from temperature extremes, they also force the RF transmission path through the building to cross very near the fire locations and anticipated plasma generation regions. Both of the locations listed in Figure 2 were tested by the UWB equipment and found to be suitable deployment locations to establish a solid RF link for data collection. The transmission location on the first floor was ultimately chosen for use during the actual exercises because it was accessible to the data collection team during the exercises. This allowed them to remove the hardware once the testing was complete without having to wait for the entire day of exercises to complete. Unfortunately, RF transmission directly through the central location of the fire on the first floor was not possible, so the transmission path had to be shifted approximately 6-feet off the side of the fire's center. The corner where the fire was located on the first floor was re-enforced with a mixture of concrete and metal fibers for heat resistance. This material was highly reflective, permitting very little RF energy to pass through it. This phenomenon was also observed and verified by Terahop's testing, discussed in the next section. An image of these re-enforced walls and a close up of the actual wall material containing the metal fibers can bee seen in Figure 3.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
RO201705190002653LZ | 1953KB | download |