【 摘 要 】
The purpose of this task was to perform an Independent Validation Review to evaluate the successful implementation and effectiveness of Safety Basis controls, including new and revised controls, to support the implementation of a new DSA/TSR for B239. This task addresses Milestone 2 of FY10 PEP 7.6.6. As the first IVR ever conducted on a LLNL nuclear facility, it was designated a pilot project. The review follows the outline developed for Milestone 1 of the PEP, which is based on the DOE Draft Guide for Performance of Independent Verification Review of Safety Basis Controls. A formal Safety Basis procedure will be developed later, based on the lessons learned with this pilot project. Note, this review is termed a ''Validation'' in order to be consistent with the PEP definition and address issues historically raised about verification mechanisms at LLNL. Validation is intended to confirm that implementing mechanisms realistically establish the ability of TSR LCO, administrative control or safety management program to accomplish its intended safety function and that the controls are being implemented. This effort should not, however, be confused with a compliance assessment against all relevant DOE requirements and national standards. Nor is it used as a vehicle to question the derivation of controls already approved by LSO unless a given TSR statement simply cannot be implemented as stated.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
RO201704240003026LZ | 1318KB | download |