Corrective Action Plan for Corrective Action Unit 562: Waste Systems, Nevada National Security Site, Nevada
NSTec Environmental Restoration
关键词: AR FACILITIES;    ASBESTOS;    BACKFILLING;    CLEANING;    CONCRETES;    DOCUMENTATION;    GREASES;    MANAGEMENT;    NEVADA TEST SITE;    REMEDIAL ACTION;    PAINTS;    SEDIMENTS;    SITE CHARACTERIZATION;    SOILS;    STEAM;    TANKS;    WASTES CAP;    CAU 562;    corrective action plan;   
DOI  :  10.2172/1030666
RP-ID  :  DOE/NV--1443
PID  :  OSTI ID: 1030666
Others  :  TRN: US1200641
美国|英语
来源: SciTech Connect
PDF
【 摘 要 】
This Corrective Action Plan has been prepared for Corrective Action Unit (CAU) 562, Waste Systems, in accordance with the Federal Facility Agreement and Consent Order (1996; as amended March 2010). CAU 562 consists of 13 Corrective Action Sites (CASs) located in Areas 2, 23, and 25 of the Nevada National Security Site. Site characterization activities were performed in 2009 and 2010, and the results are presented in Appendix A of the Corrective Action Decision Document for CAU 562. The scope of work required to implement the recommended closure alternatives is summarized. (1) CAS 02-26-11, Lead Shot, will be clean closed by removing shot. (2) CAS 02-44-02, Paint Spills and French Drain, will be clean closed by removing paint and contaminated soil. As a best management practice (BMP), asbestos tile will be removed. (3) CAS 02-59-01, Septic System, will be clean closed by removing septic tank contents. As a BMP, the septic tank will be removed. (4) CAS 02-60-01, Concrete Drain, contains no contaminants of concern (COCs) above action levels. No further action is required; however, as a BMP, the concrete drain will be removed. (5) CAS 02-60-02, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. As a BMP, the drain grates and drain pipe will be removed. (6) CAS 02-60-03, Steam Cleaning Drain, will be clean closed by removing contaminated soil. As a BMP, the steam cleaning sump grate and outfall pipe will be removed. (7) CAS 02-60-04, French Drain, was clean closed. Corrective actions were completed during corrective action investigation activities. (8) CAS 02-60-05, French Drain, will be clean closed by removing contaminated soil. (9) CAS 02-60-06, French Drain, contains no COCs above action levels. No further action is required. (10) CAS 02-60-07, French Drain, requires no further action. The french drain identified in historical documentation was not located during corrective action investigation activities. (11) CAS 23-60-01, Mud Trap Drain and Outfall, will be clean closed by removing sediment from the mud trap. As a BMP, the mud trap and outfall pipe will be removed. (12) CAS 23-99-06, Grease Trap, will be clean closed by removing sediment from the grease trap and backfilling the grease trap with grout. (13) CAS 25-60-04, Building 3123 Outfalls, will be clean closed by removing contaminated soil and the sludge-containing outfall pipe.
【 预 览 】
附件列表
Files Size Format View
RO201704210002467LZ 610KB PDF download
  文献评价指标  
  下载次数:15次 浏览次数:12次