科技报告详细信息
Generalized Test Plan for the Vitrification of Simulated High-Level -Waste Calcine in the Idaho National Laboratory???s Bench -Scale Cold Crucible Induction Melter
Vince Maio
关键词: AR FACILITIES;    ALUMINIUM;    CRUCIBLES;    DOCUMENTATION;    IDAHO NATIONAL LABORATORY;    INDUCTION;    MODIFICATIONS;    ORDERS;    PARTICULATES;    SAMPLING;    TESTING;    VITRIFICATION;    ZIRCONIUM Calcine;    Cold Crucible Induction Melter;    High Level Waste;   
DOI  :  10.2172/1037783
RP-ID  :  INL/EXT-11-23231
PID  :  OSTI ID: 1037783
Others  :  TRN: US1201759
学科分类:核能源与工程
美国|英语
来源: SciTech Connect
PDF
【 摘 要 】

This Preliminary Idaho National Laboratory (INL) Test Plan outlines the chronological steps required to initially evaluate the validity of vitrifying INL surrogate (cold) High-Level-Waste (HLW) solid particulate calcine in INL's Cold Crucible Induction Melter (CCIM). Its documentation and publication satisfies interim milestone WP-413-INL-01 of the DOE-EM (via the Office of River Protection) sponsored work package, WP 4.1.3, entitled 'Improved Vitrification' The primary goal of the proposed CCIM testing is to initiate efforts to identify an efficient and effective back-up and risk adverse technology for treating the actual HLW calcine stored at the INL. The calcine's treatment must be completed by 2035 as dictated by a State of Idaho Consent Order. A final report on this surrogate/calcine test in the CCIM will be issued in May 2012-pending next fiscal year funding In particular the plan provides; (1) distinct test objectives, (2) a description of the purpose and scope of planned university contracted pre-screening tests required to optimize the CCIM glass/surrogate calcine formulation, (3) a listing of necessary CCIM equipment modifications and corresponding work control document changes necessary to feed a solid particulate to the CCIM, (4) a description of the class of calcine that will be represented by the surrogate, and (5) a tentative tabulation of the anticipated CCIM testing conditions, testing parameters, sampling requirements and analytical tests. Key FY -11 milestones associated with this CCIM testing effort are also provided. The CCIM test run is scheduled to be conducted in February of 2012 and will involve testing with a surrogate HLW calcine representative of only 13% of the 4,000 m3 of 'hot' calcine residing in 6 INL Bin Sets. The remaining classes of calcine will have to be eventually tested in the CCIM if an operational scale CCIM is to be a feasible option for the actual INL HLW calcine. This remaining calcine's make-up is HLW containing relatively high concentrations of zirconium and aluminum, representative of the cladding material of the reprocessed fuel that generated the calcine. A separate study to define the CCIM testing needs of these other calcine classifications in currently being prepared under a separate work package (WP-0) and will be provided as a milestone report at the end of this fiscal year.

【 预 览 】
附件列表
Files Size Format View
RO201704210001643LZ 538KB PDF download
  文献评价指标  
  下载次数:11次 浏览次数:32次