American Recovery and Reinvestment Act: North Fork Skokomish Powerhouse at Cushman No. 2 Dam | |
Fischer, Steve1  McCarty, Patrick1  | |
[1] DBA Tacoma Power, WA (United States) | |
关键词: Powerhouse; Existing Dam; Fish Passage; | |
DOI : 10.2172/1095018 RP-ID : DOE-TacomaPowerNFPH--002669 PID : OSTI ID: 1095018 |
|
学科分类:再生能源与代替技术 | |
美国|英语 | |
来源: SciTech Connect | |
【 摘 要 】
The objective of this project was to add generating capacity on an in-stream flow release at Tacoma Power's Cushman hydroelectric project, Cushman No. 2 Dam, FERC Project P-460. The flow that is being used to generate additional electricity was being discharged from a valve at the base of the dam without recovery of the energy. A second objective to the project was to incorporate upstream fish passage by use of a fish collection structure attached to the draft tubes of the hydroelectric units. This will enable reintroduction of native anadromous fish above the dams which have blocked fish passage since the late 1920's. The project was funded in part by the American Recovery and Reinvestment Act through the Department of Energy, Office of Energy, Efficiency and Renewable Energy, Wind and Water Power Program.
【 预 览 】
Files | Size | Format | View |
---|---|---|---|
RO201704180001270LZ | 17067KB | download |