| Analysis of normal operation of a rockfill damwith combination of seepage-control elements:reinforced concrete face and clay-cement-concrete wall | |
| M.P. Sainov1  | |
| [1] National Research Moscow State Civil Engineering University; | |
| 关键词: concrete faced rockfill dam; cut-off wall; stress-strain state; numerical modeling; cut-off wall; stress-strain state; numerical modeling; | |
| DOI : 10.5862/MCE.64.1 | |
| 来源: DOAJ | |
【 摘 要 】
The paper considers results of stress-strain state analysis for a 87 m high rockfill dam that is located in the layer of soil foundation and has a combined seepage-control element. In the lower part of the dam as well as in its foundation there is fixed a grout curtain by using slurry trench cut-off walls, and in the upper part there is fixed a reinforced concrete face. The wall and the face are conjugated via the reinforced concrete gallery. Analyses showed that both seepage-control elements have a favorable stress-strain state: no tensile stresses occur in them. In the considered dam the reinforced concrete face operates in more favorable conditions than in a traditional dam with a reinforced concrete face. This allows recommending this type of the dam for practical application in hydraulic engineering. The alternative is proposed with the design of conjugation of a reinforced concrete face and a seepage-control wall.
【 授权许可】
Unknown