Case Studies in Thermal Engineering
Research on security technology of tower foundation based on precise control of freezing temperature field
Jie Gao1  Wei Zhao2  Wei Qin2 
[1] Corresponding author.;State Key Laboratory of Coal Resources and Safe Mining, China University of Mining and Technology, Xuzhou, Jiangsu, 221116, China;
关键词: Freezing method;    Freezing temperature field;    Tower foundation;    Precise freezing technology;    Surface deformation;    Freezing parameter optimization;   
DOI  :  
来源: DOAJ
【 摘 要 】

Freezing method is used in the main shaft slotting repair project in Chensilou Coal Mine in China. According to the actual conditions of Chensilou Coal Mine, this paper established a numerical calculation model which included the following influence factors: thermodynamic parameters, borehole layout, original formation temperature, groundwater seepage, hot water circulation protection. The calculation results show that the reasonable brine temperature for the freezing project in Chensilou Coal Mine should be controlled between -30 °C and -25 °C and the reasonable freezing time should be 160 days. When the freezing time extends to 80–120 days, the freezing front has developed to the temperature-control hole. In this case, the hot water circulation of the temperature-control hole needs to be started and the hot water temperature is not lower than 20 °C. The freezing construction was implemented in accordance with the optimized brine temperature and freezing time, and the freezing of tower foundation has been successfully avoided. The measured results show that the tower tilts to the northeast as a whole during formation freezing and the tilt values are all less than the allowable value.

【 授权许可】

Unknown   

  文献评价指标  
  下载次数:0次 浏览次数:0次