会议论文详细信息
World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium - WMCAUS
Application of Earned Value Method for evaluation the Time/Cost Consequences of Variation Orders in a Construction Project
土木建筑工程
Czemplik, Andrzej^1
Wroclaw University of Science and Technology, Wybrzeze Wyspianskiego 27, Wroclaw
50-370, Poland^1
关键词: Construction projects;    Construction works;    Decision making process;    Earned value;    Project completion;    Project cost;    Tool supporting;   
Others  :  https://iopscience.iop.org/article/10.1088/1757-899X/245/7/072028/pdf
DOI  :  10.1088/1757-899X/245/7/072028
学科分类:土木及结构工程学
来源: IOP
PDF
【 摘 要 】

The decision-making process of acceptance of the variations order (VO) for running construction project is always subjected to the risk of consequences, which are difficult to be defined. But, even having all the technical and organizational consequences identified, their impact on the project completion date and final project cost, is not easy to state. The practical methodology of using the Earned Value Method (EVM) as a tool supporting the acceptance decision of the VO being considered during construction works, is presented in the paper. The main strength of the presented concept is a quick prognosis of the final project completion date and the final project cost in case the VO is accepted.

【 预 览 】