8th International Particle Accelerator Conference
Installation management for the European XFEL main accelerator
Bousonville, M.^1 ; Eints, F.^1 ; Choroba, S.^1
DESY Deutsches Elektronen-Synchrotron, Hamburg, Germany^1
关键词: Complex machines;    European xfel;    Installation management;    Management method;   
Others  :  https://iopscience.iop.org/article/10.1088/1742-6596/874/1/012016/pdf
DOI  :  10.1088/1742-6596/874/1/012016
来源: IOP
PDF
【 摘 要 】

By end of 2016, the main accelerator of the European XFEL was completed. To build this complex machine in a minimum of time, certain management methods were introduced in mid 2015, which accelerated the installation process substantially. In the following 64 weeks additional 84 % of the main accelerator were set up. This was possible due to an improved planning, the reinforcement of two teams as well as a permanent controlling and optimizing of the installation process. In this paper, the installation process from July 2015 to end 2016 and the measures, which speeded up the workflow, are described.

【 预 览 】
附件列表
Files Size Format View
Installation management for the European XFEL main accelerator 997KB PDF download
  文献评价指标  
  下载次数:19次 浏览次数:23次