CITIES 2016 International Conference: Coastal Planning for Sustainable Maritime Development
Project delay analysis of HRSG
Silvianita^1 ; Novega, A.S.^1 ; Rosyid, D.M.^1 ; Suntoyo^1
Department of Ocean Engineering, Faculty of Marine Technology, Institut Teknologi Sepuluh Nopember, Indonesia^1
关键词: Bow-tie analysis;    Construction process;    Event tree analysis;    Fabrication process;    Heat recovery steam generators;    Preventive measures;    Project delays;    Risk matrix;   
Others  :  https://iopscience.iop.org/article/10.1088/1755-1315/79/1/012036/pdf
DOI  :  10.1088/1755-1315/79/1/012036
来源: IOP
PDF
【 摘 要 】

Completion of HRSG (Heat Recovery Steam Generator) fabrication project sometimes is not sufficient with the targeted time written on the contract. The delay on fabrication process can cause some disadvantages for fabricator, including forfeit payment, delay on HRSG construction process up until HRSG trials delay. In this paper, the author is using semi quantitative on HRSG pressure part fabrication delay with configuration plant 1 GT (Gas Turbine) + 1 HRSG + 1 STG (Steam Turbine Generator) using bow-tie analysis method. Bow-tie analysis method is a combination from FTA (Fault tree analysis) and ETA (Event tree analysis) to develop the risk matrix of HRSG. The result from FTA analysis is use as a threat for preventive measure. The result from ETA analysis is use as impact from fabrication delay.