| 3rd International Symposium on Resource Exploration and Environmental Science | |
| Concrete Construction of Flood Discharge and Sand-washing Sluice Bottom Slab of Angu Hydropower Station | |
| 生态环境科学 | |
| Chen, Jie^1 ; Xu, Xiaoyi^1 | |
| Skills Training Center of State Grid Sichuan Electric Power Company, Chengdu | |
| 611133, China^1 | |
| 关键词: Concrete construction methods; Construction effect; Construction procedures; Construction progress; Construction scheme; Hydropower stations; Protective measures; Wear resistant; | |
| Others : https://iopscience.iop.org/article/10.1088/1755-1315/300/2/022108/pdf DOI : 10.1088/1755-1315/300/2/022108 |
|
| 学科分类:环境科学(综合) | |
| 来源: IOP | |
PDF
|
|
【 摘 要 】
Based on the analysis of the concrete construction of the bottom slab of flood-discharge and sand-wash sluice in Angu Hydropower Station, this paper expounds the construction characteristics and difficulties, construction procedures, concrete construction of concrete stilling pool in conventional position, concrete construction of overflow and retaining wall, concrete construction methods and measures in special position, etc. Especially, the concrete stratified partition of the bottom slab of flood-discharge and sand-wash sluice and the typical partition of stilling pool have their unique features. The overflow surface concrete adopts self-designed, processed and manufactured stereotyped drawing dies. And after concreting, we use bamboo springboards and protective measures to keep warm in time. The construction scheme is reasonable in design, meets the requirements of construction progress, has no safety accidents, and achieves good construction effect. It has certain reference value for the concrete construction of bottom slab of flood discharge and sand washing sluice of similar projects.
【 预 览 】
| Files | Size | Format | View |
|---|---|---|---|
| Concrete Construction of Flood Discharge and Sand-washing Sluice Bottom Slab of Angu Hydropower Station | 735KB |
PDF