会议论文详细信息
2019 5th International Conference on Energy Materials and Environment Engineering | |
The Research and Control Measures of the Influence on the Complicated tie-line and the Bridge under the Shield Tunnel | |
能源学;生态环境科学 | |
Wang, Hao^1^2 ; Liu, Junyan^1^2 ; Zhang, Liangliang^3 | |
College of Civil Architecture, University of Jinan, Jinan, Shandong | |
250022, China^1 | |
Res. Center of Underground Construction Supporting and Risk Control Technology of Shandong Province, Jinan, Shandong | |
250022, China^2 | |
China Railway Siyuan Survey and Design Group Co.LTD., Wuhan, Hubei | |
430000, China^3 | |
关键词: Analysis and calculations; Deformation control; Monitoring information; Rail transit lines; Reinforcement measures; Shield tunnelling method; Three dimensional finite element analysis; Three dimensional finite elements; | |
Others : https://iopscience.iop.org/article/10.1088/1755-1315/295/4/042081/pdf DOI : 10.1088/1755-1315/295/4/042081 |
|
学科分类:环境科学(综合) | |
来源: IOP | |
【 摘 要 】
The analysis and calculation of the influence of Shield Tunnels Crossing Existing Railways and bridges considering the time-space effect is of great significance to the risk control of shield tunnels. Taking the long-distance bus station-production Road station section of Jinan rail transit line R2 as an example, shield tunnelling method is used to construct the shield tunnels in this section, and the shield tunnels are crossed under the Beibei Bridge of Beijing-Jiaozuo Liaison Line and Beijing-Shanghai Link In order to study the influence of shield tunnelling on railway and bridge piles, three-dimensional finite element numerical analysis method is used to establish a three-dimensional finite element analysis model through MIDAS/GTS. The position relationship of shield tunnels, railways and bridge piles and the shield tunnelling distance are simulated. The stress of railway subgrade and pile foundation caused by shield tunnelling is analyzed. The result of deformation is within the allowable value of deformation control of railway and bridge. Without any reinforcement measures, through monitoring the deformation of subgrade and bridge, timely feedback of monitoring information and timely adjustment of shield tunnelling parameters, shield tunnelling can safely Cross railway and bridge. The development of similar projects will provide relevant reference.【 预 览 】
Files | Size | Format | View |
---|---|---|---|
The Research and Control Measures of the Influence on the Complicated tie-line and the Bridge under the Shield Tunnel | 697KB | download |