会议论文详细信息
29th IAHR Symposium on Hydraulic Machinery and Systems
A runner modernization in a Deriaz turbine hydropower station
Kikuta, H.^1 ; Suzuki, R.^1 ; Nakamura, S.^1 ; Anciger, D.^2
Voith Fuji Hydro K.K., Tanabeshinden, Kawasaki-ku, Kawasaki
210-9830, Japan^1
Voith Hydro Holding GmbH and Co. KG, Germany^2
关键词: CFD technologies;    Energy productions;    Hydraulic parts;    Hydropower stations;    Model tests;    Modernization projects;    State of the art;    Turbine modes;   
Others  :  https://iopscience.iop.org/article/10.1088/1755-1315/240/2/022059/pdf
DOI  :  10.1088/1755-1315/240/2/022059
来源: IOP
PDF
【 摘 要 】

This paper introduces our experience of a Deriaz turbine modernization project. N hydropower station in Japan, with the 50MW Deriaz turbine (turbine mode only), had been operated for approximately 50 years. Not only for the purpose of the maintenance but also for the energy production increase, the turbine modernization was planned along with the scheduled overhaul. The modernization scope of the hydraulic parts was discussed and the blade only option was selected. In the new blade development, the existing mechanical limits were the restriction and the lack of recent experiences in Deriaz turbine development was a challenge. For the challenge, a development procedure special for the project was introduced, using state of the art CFD technology and the model test. As the result, within the existing mechanical limits, 3% gain in performance at the full load has been achieved and the performance was successfully confirmed in the model test and the prototype site test.